Apply for a new electricity (BESCOM) connection
Get a new domestic power connection through BESCOM's online application with ownership and ID proof.
Authority
BESCOM
Mode
Online
Time
7–30 days after document verification
Cost
Connection + meter + security deposit (varies by load)
Steps
- 1
Apply online
Use the BESCOM online new-connection service and fill the application with the sanctioned load you need.
- 2
Upload documents
Attach ownership, ID and the wiring completion certificate from a licensed electrician.
- 3
Estimation
BESCOM inspects and issues a cost estimate for cabling, meter and deposit.
- 4
Pay the estimate
Pay online; book the meter installation.
- 5
Meter installation
A BESCOM team installs the meter and energises the connection.